Construction Public Notice

2480 Bancroft Way, Berkeley CA

Project Description:

·       Construction of an 8-story building, consisting of 28 apartment units with commercial space below.

Construction Activities: Major phases of construction to include the following –

·       Demo of existing building and hardscape.

·       Excavation and grading to follow for preparation of the building foundation.

·       Underground utilities.

·       Forming and subsequent pouring of concrete foundation, walls, and podium slabs to occur.

·       Five stories of vertical framing including exterior and interior building finishes.

·       Site improvements including landscape, sidewalks, etc.

·       Daily construction activities one can expect are use of hand tools (hammer, drills, etc.), hauling and hoisting of material, construction equipment such as bobcats, backhoes, reach lifts running for various activities.

Anticipated General Schedule:

·       Demo/Grading (October 2023 – December 2023)

·       Concrete Construction (December 2023 – March 2024)

·       Framing (March 2024 – November 2024)

·       Façade and Finishes (September 2024 – June 2025)

Daily Construction Schedule:

·       Work will Commence 7am-6pm Monday through Friday

·       This project is approved for Saturday work if needed 9am – 4pm.

·       Expected Duration: 19 Months

Noise Management Individuals:

·       Dave de Jong (510) 307-5678 Ex. 107 – Construction Noise Liaison

Project Website:

https://www.westbuilders.net/2480bancroft