Construction Public Notice
2587 Telegraph Ave, Berkeley CA
Project Description:
Construction of an 8-story building, consisting of 52 apartment units.
Construction Activities:
Major phases of construction to include the following:
Demo of existing building and hardscape.
Installation of shoring along the east property line
Excavation and grading to follow for preparation of the building foundation.
Underground utilities.
Forming and subsequent pouring of concrete foundation and podium
Five stories of vertical framing including exterior and interior building finishes
Site improvements including landscape, sidewalks, etc.
Daily construction activities one can expect are use of hand tools (hammer, drills, etc.), hauling and hoisting of material, construction equipment such as backhoes, reach lifts, compressors, etc.
Anticipated General Schedule and Construction Phases:
Demo, Shoring, Grading & Utilities (September - November 2024)
Concrete Construction (November 2024 – March 2025)
Framing (March 2025 – September 2025)
Façade and Finishes (September 2025 – June 2026)
Site Improvements, Landscaping, Sidewalks, Etc. (March 2026 – July 2026)
Daily Construction Schedule:
Work will Commence 7am-6pm Monday through Friday
This project is approved for Saturday work if needed 9am – 4pm.
Expected Start: September 2024
Expected Finish: Q3 2026
Noise Management Individuals:
Kevin Webb (510) 307-5678
Project Website:
https://www.westbuilders.info/2587telegraph