Construction Public Notice

3030 Telegraph Ave. Berkeley CA

Project Description:

  • Construction of a 5-story building, consisting of 144 apartment units with commercial space below.

Construction Activities: Major phases of construction to include the following –

  • Demo of existing building and hardscape.

  • Excavation and grading to follow for preparation of the building foundation.

  • Underground utilities.

  • Forming and subsequent pouring of concrete foundation, walls, and podium slabs to occur.

  • Five stories of vertical framing including exterior and interior building finishes.

  • Site improvements including landscape, sidewalks, etc.

  • Daily construction activities one can expect are use of hand tools (hammer, drills, etc.), hauling and hoisting of material, construction equipment such as crane, bobcats, backhoes, reach lifts, compressors, etc.

Anticipated General Schedule:

  • Demo, Grading (August 2024 - September 2024)

  • Concrete Construction (October 2024 – November 2024)

  • Framing (November 2024 – April 2025)

  • Façade and Finishes (March 2025 – December 2025)

  • Site Improvements, Landscaping, Sidewalks, Etc. (July 2025 – December 2025)

Daily Construction Schedule:

  • Work will Commence 7am-6pm Monday through Friday

  • This project is approved for Saturday work if needed 9am – 4pm.

  • Expected Duration: 20 Months

Noise Management Individuals:

·       David Neuville (510) 775-3382

Project Website:

·       https://www.westbuilders.net/3030telegraph